Innisfail Turf Club
Completed
Start date
June 2019
Estimated completion date
June 2021
Cost
$500,000
Location
Innisfail Turf Club
The project entailed removing the reverse camber from the 500m to the 900m and the 1100m to the 1500m, installation and rectification of the inside/outside rail, installation of additional surface drainage improvements to the track and installation of a new water bore that will provide water to the facility and broader community use.
Project Timeline
Year | Action |
---|---|
June 2019 | CRP Funding Approval – Round 1 |
2019/2020 | Complete Design and Approvals |
Nov 2020 | Commence construction |
June 2021 | Project completion |
Project Update
The Innisfail Turf Club Course Proper rectification works was completed between December 2020 to June 2021. The project cost roughly $500,000 to complete.