Longreach Jockey Club
Completed
Start date
June 2019
Estimated completion date
March 2021
Cost
$82,000
Location
Longreach Jockey Club
Under CRP Round 1 the Longreach Jockey Club were successful in obtaining funding for the replacement of their existing judge’s tower.
Project Timeline
Year | Action |
---|---|
June 2019 | CRP Funding Approval – Round 1 |
2019/2020 | Complete Design and Approvals |
Jan 2021 | Commence construction |
March 2021 | Project completion |
Project Update
The construction works were completed in early March 2021 and has been used for multiple race meetings this year.